Universal Housing App NEW Capacity Building Continuum of Care Coordinated Entry System FileShare Funding HMIS Homeless Count Resource Management System Housing Extension LA-HOP Legislative Affairs MyOrg People New Policy Veterans By Name EGMS (LAHSA staff) EGMSAll Apps
LAHSA Logo

Submission Deadline: June 4, 2021, 2:00 PM

May 11, 2021 | June 17, 2021 | 3,910 total views

RFI Timeline

Date Time Details  
May 11, 2021   RFI Release
May 18, 2021 2:00 PM Written Questions Deadline
June 4, 2021 2:00 PM Submission Deadline

RFI Documents

2021 Subrecipient Project Replacement for CoC Joint TH-RRH and RRH Program RFI

2021 Subrecipient Project Replacement for CoC Joint TH-RRH and RRH Program RFI - Addendum #1

2021 Subrecipient Project Replacement for CoC Joint TH-RRH and RRH Program RFI - Q&A

 

RFI Submission Documents

2021 Subrecipient Project Replacement for CoC Joint TH-RRH and RRH Program RFI Buedget Template

2021 Subrecipient Project Replacement for CoC Joint TH-RRH and RRH Program RFI Suvey Link

2021 Subrecipient Project Replacement for CoC Joint TH-RRH and RRH Program RFI Survey Questions - Transitional Housing Component and Rapid Re-Housing Component

2021 Subrecipient Project Replacement for CoC Joint TH-RRH and RRH Program RFI Survey Questions - Standalone Rapid Re-Housing

 

Scope of Required Services (SRS)

Scope of Required Services (SRS) TH-RRH Program for Domestic Violence/Intimate Partner Violence (DV/IPV) Survivors

Scope of Required Services (SRS) Rapid Re-Housing for DV/IPV Survivors

 

Related

FY 2022 CoC Program NOFO
2022 Special Nofo To Address Unsheltered And Rural Homelessness
2022 COC Comparable Database For Survivors Of Domestic Violence RFP
FY 2021 CoC Program NOFO
2022 Youth Homelessness Demonstration Program RFP